Village of Sombra Main Pumping Station Rehabilitation
Federal contribution
$100,000
Federal share50%
of $200.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 24, 2017
20182019
Built
Approved 3 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Township of St. Clair
- Construction start
- Apr 14, 2017(actual)
- Construction end
- Feb 4, 2019(actual)
Against the original forecast
- Construction start4 months earlyforecast Jul 31, 2017
- Construction end3 weeks earlyforecast Feb 28, 2019
Also in St. Clair
- Rehabilitation of the Holt Line Bridge over the Sydenham River$600.0K
- Village of Port Lambton Wastewater Lagoons Optimization$570.9K
- Village of Sombra Wastewater Lagoon Optimization$374.8K
- New Indirect Plant and 2nd refrigerant for Rink#2$308.5K
- Village of Port Lambton Main Pumping Station Rehabilitation$100.0K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48365 in the federal list. How to read these figures.