LaHave River Straight Pipe Remediation

Lunenburg, Nova Scotia

completeWastewaterSCF
Federal contribution
$3.2M
$3,185,549
Federal share33%

of $9.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 29, 2017
201820192020202120222023
Built

Approved 3 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Construction start
Apr 30, 2018(actual)
Construction end
Mar 1, 2023(actual)

Against the original forecast

  • Construction start13 months lateforecast Apr 1, 2017
  • Construction end2 months lateforecast Dec 15, 2022