LaHave River Straight Pipe Remediation
Federal contribution
$3.2M
$3,185,549
Federal share33%
of $9.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 29, 2017
201820192020202120222023
Built
Approved 3 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Municipality of the District of Lunenburg
- Construction start
- Apr 30, 2018(actual)
- Construction end
- Mar 1, 2023(actual)
Against the original forecast
- Construction start13 months lateforecast Apr 1, 2017
- Construction end2 months lateforecast Dec 15, 2022