Wastewater Treatment Plant Upgrade with Sequencing Batch Reactor (SBR)
Federal contribution
$4.0M
$3,993,200
Federal share33%
of $12.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 13, 2023
today
2023202420252026
BuiltForecast
Approved 4 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Town of Lunenburg
- Construction start
- May 21, 2025(actual)
- Construction end
- Sep 30, 2026(forecast)
Also in Lunenburg