Back to projects

Mont-Cervin, phases 2, 3 and 4

Lac-Beauport, Quebec

completeWastewaterCWWF
Federal contribution
$3.2M
$3,239,999
Federal share35%

of $9.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 1, 2017
20172018
Built

Approved 2 months before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Apr 1, 2017(actual)
Construction end
Sep 30, 2018(actual)

Against the original forecast

  • Construction start4 weeks earlyforecast May 1, 2017
  • Construction end6 months earlyforecast Mar 31, 2019

Also in Lac-Beauport

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48394 in the federal list. How to read these figures.