Construction of the new Cooksville Creek Flood Storage Facility - near Eglinton Ave and Kennedy Rd
Federal contribution
$3.2M
$3,205,845
Federal share50%
of $6.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 23, 2017
2018
Built
Approved 3 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Mississauga
- Construction start
- Oct 23, 2017(actual)
- Construction end
- Aug 20, 2018(actual)
Against the original forecast
- Construction start3 weeks lateforecast Oct 1, 2017
- Construction end6 weeks earlyforecast Sep 30, 2018