Water Treatment Plant Upgrades

Buena Vista, Saskatchewan

completeDrinking WaterCWWF
Federal contribution
$428,250
Federal share50%

of $856.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 11, 2017
20172018201920202021
Built

Approved 3 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Village of Buena Vista
Construction start
Aug 19, 2019(actual)
Construction end
Sep 1, 2021(actual)

Against the original forecast

  • Construction start11 months lateforecast Oct 1, 2018
  • Construction end5 months lateforecast Mar 31, 2021

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48413 in the federal list. How to read these figures.