Drinking water upgrade
Federal contribution
$1.4M
$1,388,587
Federal share50%
of $2.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 1, 2017
2017
Built
Approved 2 months before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Parish Municipality of Saint-Urbain
- Construction start
- Apr 1, 2017(actual)
- Construction end
- Sep 15, 2017(actual)
Against the original forecast
- Construction start3 months earlyforecast Jul 3, 2017
- Construction end18 months earlyforecast Mar 31, 2019
Also in Saint-Urbain
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48417 in the federal list. How to read these figures.