Drinking water upgrade

Saint-Urbain, Quebec

completeDrinking WaterCWWF
Federal contribution
$1.4M
$1,388,587
Federal share50%

of $2.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 1, 2017
2017
Built

Approved 2 months before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Apr 1, 2017(actual)
Construction end
Sep 15, 2017(actual)

Against the original forecast

  • Construction start3 months earlyforecast Jul 3, 2017
  • Construction end18 months earlyforecast Mar 31, 2019

Also in Saint-Urbain

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48417 in the federal list. How to read these figures.