Restoration of the Cooksville Creek Stormwater Erosion Control - Mississauga Valley Blvd to Central Pkwy E
Federal contribution
$738,651
Federal share50%
of $1.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 23, 2017
201820192020
Built
Approved 2 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Mississauga
- Construction start
- Sep 30, 2017(actual)
- Construction end
- Jun 30, 2020(actual)
Against the original forecast
- Construction end6 months lateforecast Dec 31, 2019
Also in Mississauga
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48428 in the federal list. How to read these figures.