Construction of Foundation Drainage Collector (FDC) Pumping Station and Utility Trench dewatering system - in the vicinity of Black Walnut Trail and Cactus Gate (Lisgar)
Federal contribution
$1.0M
$1,003,847
Federal share50%
of $2.0M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMay 23, 2017
ApprovedMar 27, 2018
20172018201920202021
Built
Approved 10 months after the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Mississauga
- Construction start
- Jan 1, 2017(actual)
- Construction end
- Apr 1, 2021(actual)