Rehabilitation of the Stormwater Management Facilities 0801, 4403, 5701 and 5702
Federal contribution
$803,655
Federal share47%
of $1.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 23, 2017
2018
Built
Approved 3 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Mississauga
- Construction start
- Dec 1, 2017(actual)
- Construction end
- May 30, 2018(actual)
Against the original forecast
- Construction start2 months lateforecast Oct 1, 2017
- Construction end4 months earlyforecast Sep 30, 2018
Also in Mississauga
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48432 in the federal list. How to read these figures.