Design of the Cooksville Creek Flood Storage Facility - Mississauga Valley
Federal contribution
$236,418
Federal share50%
of $472.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 23, 2017
2017201920212023
Built
Approved 3 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Mississauga
- Construction start
- Mar 16, 2017(actual)
- Construction end
- Dec 31, 2022(actual)
Against the original forecast
- Construction start2 weeks lateforecast Mar 1, 2017
- Construction end4 weeks lateforecast Dec 1, 2022
Also in Mississauga
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48434 in the federal list. How to read these figures.