Wastewater Lagoon Upgrade

Halbrite, Saskatchewan

completeWastewaterCWWF
Federal contribution
$495,000
Federal share50%

of $990.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 11, 2017
2017201820192020
Built

Approved 3 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Village of Halbrite
Construction start
Apr 1, 2019(actual)
Construction end
Feb 18, 2020(actual)

Against the original forecast

  • Construction start13 months lateforecast Mar 1, 2018
  • Construction end4 months lateforecast Oct 8, 2019

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48457 in the federal list. How to read these figures.