Water Treatment Plant Upgrade

Kelvington, Saskatchewan

completeDrinking WaterCWWF
Federal contribution
$566,704
Federal share50%

of $1.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 11, 2017
201720182019
Built

Approved 3 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Kelvington
Construction start
Dec 18, 2017(actual)
Construction end
Jan 15, 2019(actual)

Against the original forecast

  • Construction start7 weeks lateforecast Nov 1, 2017
  • Construction end2 months earlyforecast Mar 29, 2019