New Lagoon
Federal contribution
$550,790
Federal share50%
of $1.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 11, 2017
201720182019
Built
Approved 3 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Village of Mervin
- Construction start
- Sep 15, 2017(actual)
- Construction end
- Dec 12, 2018(actual)
Against the original forecast
- Construction end4 months earlyforecast Mar 31, 2019
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48469 in the federal list. How to read these figures.