Sewage Lagoon Upgrade
Federal contribution
$562,237
Federal share50%
of $1.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 11, 2017
2017
Built
Approved 3 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Village of Stockholm
- Construction start
- Jul 18, 2017(actual)
- Construction end
- Nov 12, 2017(actual)
Against the original forecast
- Construction start3 months lateforecast May 1, 2017
- Construction end10 months earlyforecast Sep 7, 2018
Also in Stockholm
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48474 in the federal list. How to read these figures.