Water Treatment Plant and Reservoir Upgrade
Federal contribution
$192,500
Federal share50%
of $385.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 11, 2017
201720182019
Built
Approved 3 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Village of Tantallon
- Construction start
- Sep 5, 2017(actual)
- Construction end
- Dec 12, 2018(actual)
Against the original forecast
- Construction start11 months lateforecast Oct 1, 2016
- Construction end3 weeks earlyforecast Dec 31, 2018
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48476 in the federal list. How to read these figures.