Rehabilitation of water, sewer and road infrastructure on Plaunt Street (Phase2) from Railway Avenue to dead end
Federal contribution
$517,331
Federal share25%
of $2.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 23, 2017
2018
Built
Approved 3 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Renfrew
- Construction start
- May 15, 2017(actual)
- Construction end
- Oct 3, 2018(actual)
Against the original forecast
- Construction start6 months lateforecast Nov 1, 2016
- Construction end5 weeks lateforecast Aug 31, 2018