Water Servicing Options Study
Federal contribution
$47,583
Federal share33%
of $145.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 24, 2017
2018
Built
Approved 3 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Township of Evanturel
- Construction start
- Jul 14, 2017(actual)
- Construction end
- Aug 31, 2018(actual)
Against the original forecast
- Construction start9 months lateforecast Sep 30, 2016
- Construction end4 months earlyforecast Dec 31, 2018
Also in Evanturel
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48505 in the federal list. How to read these figures.