Upgrades to the Matachewan Stormwater Control System Located in an Area Covering 10 Municipal Streets between Calbeck Avenue and Helen Avenue

Matachewan, Ontario

completeWastewaterCWWF
Federal contribution
$50,000
Federal share50%

of $100.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 24, 2017
2018
Built

Approved 3 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Township of Matachewan
Construction start
Nov 1, 2017(actual)
Construction end
Oct 31, 2018(actual)

Against the original forecast

  • Construction start6 months lateforecast May 1, 2017
  • Construction end13 months lateforecast Sep 30, 2017