Installation of Catch Basin and Infiltration Gallaries to Combat Localized Flooding in Various Loacations

North Dumfries, Ontario

completeWastewaterCWWF
Federal contribution
$12,988
Federal share26%

of $50.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 23, 2017
201820192020
Built

Approved 3 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Township of North Dumfries
Construction start
Jul 11, 2017(actual)
Construction end
Mar 31, 2020(actual)

Against the original forecast

  • Construction start5 months lateforecast Feb 1, 2017
  • Construction end6 months lateforecast Sep 30, 2019