Niagara Falls Water Treatment Plant Lead Abatement & Filter Repairs (Plant 1 & 2)

Niagara, Ontario

completeDrinking WaterCWWF
Federal contribution
$1.9M
$1,872,000
Federal share45%

of $4.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 24, 2017
2018201920202021
Built

Approved 2 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Nov 17, 2017(actual)
Construction end
Feb 12, 2021(actual)

Against the original forecast

  • Construction end7 weeks earlyforecast Mar 31, 2021

Also in Niagara

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48591 in the federal list. How to read these figures.