Design of Damaged Storm Pipe Off Henderson Drive
Federal contribution
$59,128
Federal share39%
of $150.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 24, 2017
201820192020
Built
Approved 2 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Aurora
- Construction start
- Jan 1, 2019(actual)
- Construction end
- Mar 31, 2020(actual)
Against the original forecast
- Construction start4 months earlyforecast May 1, 2019
Also in Aurora
- HVAC Upgrades; Bottle fill station; Gym Divider Wall$7.6M
- HVAC upgrades in schools and portables; Windows replacement, Portable replacements$6.3M
- HVAC System in portable classrooms$4.2M
- Cooling Centres; Window Replacement$4.1M
- HVAC Upgrades (schools); Wifi Access Points and network switches; Security Access (communication/paging system)$3.8M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48604 in the federal list. How to read these figures.