Decommissioning Wells Street Public School Sanitary Sewer
Federal contribution
$78,323
Federal share26%
of $300.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 24, 2017
2017
Built
Approved 2 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Aurora
- Construction start
- Sep 15, 2016(actual)
- Construction end
- Jul 30, 2017(actual)
Against the original forecast
- Construction start7 months earlyforecast Apr 15, 2017
- Construction end5 months earlyforecast Dec 31, 2017
Also in Aurora
- HVAC Upgrades; Bottle fill station; Gym Divider Wall$7.6M
- HVAC upgrades in schools and portables; Windows replacement, Portable replacements$6.3M
- HVAC System in portable classrooms$4.2M
- Cooling Centres; Window Replacement$4.1M
- HVAC Upgrades (schools); Wifi Access Points and network switches; Security Access (communication/paging system)$3.8M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48606 in the federal list. How to read these figures.