Reconstruction of Existing Watermain and Storm Sewer Infrastructure on Algonquin Crescent and Haida Drive
Federal contribution
$459,550
Federal share50%
of $919.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 24, 2017
Built
Approved 2 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Aurora
- Construction start
- Apr 15, 2017(actual)
- Construction end
- Nov 30, 2017(actual)
Against the original forecast
- Construction end4 weeks earlyforecast Dec 31, 2017
Also in Aurora
- HVAC Upgrades; Bottle fill station; Gym Divider Wall$7.6M
- HVAC upgrades in schools and portables; Windows replacement, Portable replacements$6.3M
- HVAC System in portable classrooms$4.2M
- Cooling Centres; Window Replacement$4.1M
- HVAC Upgrades (schools); Wifi Access Points and network switches; Security Access (communication/paging system)$3.8M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48607 in the federal list. How to read these figures.