Upgrade of sanitary sewer on Centennial Drive from Resource Road approximately 1544m southerly

Kingston, Ontario

completeWastewaterCWWF
Federal contribution
$838,221
Federal share43%

of $2.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 23, 2017
2018
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Kingston
Construction start
May 1, 2017(actual)
Construction end
Jul 30, 2018(actual)

Against the original forecast

  • Construction start4 months lateforecast Jan 1, 2017
  • Construction end5 months earlyforecast Dec 31, 2018