Back to projects

Process and Control Equipment Upgrades to the Dalton Avenue Sewage Pumping Station

Kingston, Ontario

underwayWastewaterCWWF
Federal contribution
$900,000
Federal share50%

of $1.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 23, 2017
20182019202020212022
BuiltForecast
Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Kingston
Construction start
May 1, 2017(actual)
Construction end
Oct 31, 2021(forecast)

Against the original forecast

  • Construction start4 months lateforecast Jan 1, 2017

Also in Kingston