Upgrade of water main on Cataraqui Woods Drive from Midland Ave to Clyde Court

Kingston, Ontario

completeDrinking WaterCWWF
Federal contribution
$750,000
Federal share50%

of $1.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 23, 2017
2018
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Kingston
Construction start
May 1, 2017(actual)
Construction end
Jun 30, 2018(actual)

Against the original forecast

  • Construction start4 months lateforecast Jan 1, 2017
  • Construction end3 months lateforecast Mar 31, 2018

Also in Kingston

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48613 in the federal list. How to read these figures.