Thornbury Wastewater Treatment Plant Ultraviolet (UV) Replacement

The Blue Mountains, Ontario

completeWastewaterCWWF
Federal contribution
$186,681
Federal share33%

of $561.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 16, 2017
ApprovedMar 27, 2018
2018
Built

Approved 9 months after the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of The Blue Mountains
Construction start
Feb 6, 2017(actual)
Construction end
May 31, 2018(actual)

Against the original forecast

  • Construction start13 months earlyforecast Feb 28, 2018