Thornbury Wastewater Treatment Plant Ultraviolet (UV) Replacement
Federal contribution
$186,681
Federal share33%
of $561.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 16, 2017
ApprovedMar 27, 2018
2018
Built
Approved 9 months after the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of The Blue Mountains
- Construction start
- Feb 6, 2017(actual)
- Construction end
- May 31, 2018(actual)
Against the original forecast
- Construction start13 months earlyforecast Feb 28, 2018
Also in The Blue Mountains
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48639 in the federal list. How to read these figures.