Belgrave Water System Capital Upgrades & Rehabilitation
Federal contribution
$36,957
Federal share40%
of $92.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 26, 2017
2018
Built
Approved 2 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Municipality of Morris-Turnberry
- Construction start
- Sep 1, 2017(actual)
- Construction end
- Sep 30, 2018(actual)
Against the original forecast
- Construction start8 months lateforecast Jan 1, 2017
- Construction end3 months lateforecast Jun 30, 2018