Drainage improvements and Low Impact Development at Birch Point

Thunder Bay, Ontario

completeWastewaterCWWF
Federal contribution
$60,320
Federal share50%

of $120.6K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMay 24, 2017
ApprovedMar 27, 2018
2018
Built

Approved 10 months after the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Jun 1, 2017(actual)
Construction end
Oct 1, 2018(actual)

Against the original forecast

  • Construction end3 months lateforecast Jul 1, 2018