Back to projects

Extension of Catch Basins in Multiple Locations to Improve Local Drainage

Thunder Bay, Ontario

completeWastewaterCWWF
Federal contribution
$25,000
Federal share50%

of $50.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 24, 2017
2018
Built

Approved 2 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Jun 1, 2017(actual)
Construction end
Oct 1, 2018(actual)

Also in Thunder Bay