Post Assessment Repairs to Stormwater Outfalls
Federal contribution
$12,500
Federal share50%
of $25.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 24, 2017
2018
Built
Approved 2 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Corporation of the City of Thunder Bay
- Construction start
- Jun 1, 2017(actual)
- Construction end
- Jun 30, 2018(actual)
Against the original forecast
- Construction end3 months earlyforecast Oct 1, 2018
Also in Thunder Bay
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48729 in the federal list. How to read these figures.