Back to projects

Construction of 375-450mm Stormwater Separation Sewer on Selkirk Street - Arthur Street to Cuthbertson Place and Cuthbertson Place - Selkirk St to Franklin St.

Thunder Bay, Ontario

completeWastewaterCWWF
Federal contribution
$57,891
Federal share50%

of $115.8K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMay 24, 2017
ApprovedMar 27, 2018
2018
Built

Approved 10 months after the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Jun 1, 2017(actual)
Construction end
Oct 1, 2018(actual)

Also in Thunder Bay