Back to projects

Cement Mortar Lining of 150mm Cast Iron Watermains in the Hallam Street/Dewe Avenue/Dacre Street/Hodder Avenue Grid

Thunder Bay, Ontario

completeDrinking WaterCWWF
Federal contribution
$369,847
Federal share23%

of $1.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 24, 2017
2018
Built

Approved 2 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Jun 1, 2017(actual)
Construction end
Dec 31, 2017(actual)

Against the original forecast

  • Construction end3 months earlyforecast Mar 31, 2018

Also in Thunder Bay

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48756 in the federal list. How to read these figures.