Sanitary Sewer Collection System Rehabilitation

Tecumseh, Ontario

completeWastewaterCWWF
Federal contribution
$1.0M
$1,038,442
Federal share46%

of $2.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 12, 2017
201820192020
Built

Approved 3 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Tecumseh
Construction start
Aug 1, 2017(actual)
Construction end
Mar 31, 2020(actual)

Against the original forecast

  • Construction start3 months lateforecast Apr 17, 2017