Upgrading of On Demand Scheduling System - GoBus

St. John's, Newfoundland and Labrador

completePublic TransitPTIF
Federal contribution
$263,217
Federal share48%

of $544.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 3, 2017
2018
Built

Approved 4 weeks before the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
City of St. John's
Construction start
May 2, 2017(actual)
Construction end
Feb 28, 2018(actual)

Against the original forecast

  • Construction start3 months lateforecast Feb 1, 2017
  • Construction end10 months earlyforecast Dec 31, 2018

Also in St. John's

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48805 in the federal list. How to read these figures.