Renewal of water pipes

Saint-Pie, Quebec

completeDrinking WaterCWWF
Federal contribution
$1.1M
$1,120,042
Federal share48%

of $2.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 24, 2017
2017
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Saint-Pie
Construction start
Jun 13, 2016(actual)
Construction end
Nov 5, 2017(actual)

Against the original forecast

  • Construction start3 months earlyforecast Sep 8, 2016
  • Construction end5 months earlyforecast Mar 31, 2018