Renewal of water pipes

Pont-Rouge, Quebec

completeDrinking WaterCWWF
Federal contribution
$1.1M
$1,133,349
Federal share50%

of $2.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 1, 2017
20172018
Built

Approved 6 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Pont-Rouge
Construction start
Apr 24, 2017(actual)
Construction end
Oct 24, 2018(actual)

Against the original forecast

  • Construction start11 months lateforecast May 16, 2016
  • Construction end5 months earlyforecast Mar 31, 2019

Also in Pont-Rouge

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48815 in the federal list. How to read these figures.