Renewal of water pipes
Federal contribution
$1.1M
$1,133,349
Federal share50%
of $2.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 1, 2017
20172018
Built
Approved 6 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Pont-Rouge
- Construction start
- Apr 24, 2017(actual)
- Construction end
- Oct 24, 2018(actual)
Against the original forecast
- Construction start11 months lateforecast May 16, 2016
- Construction end5 months earlyforecast Mar 31, 2019
Also in Pont-Rouge