Renewal of water pipes

Ham-Nord, Quebec

completeDrinking WaterCWWF
Federal contribution
$160,985
Federal share39%

of $409.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 20, 2017
20172018
Built

Approved 3 months before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Township of Ham-Nord
Construction start
Aug 27, 2018(actual)
Construction end
Oct 15, 2018(actual)

Against the original forecast

  • Construction start15 months lateforecast May 14, 2017
  • Construction end5 months earlyforecast Mar 31, 2019