Replacement of the drinking water reservoir and conduct to the rank of the Forges

Sainte-Geneviève-de-Batiscan, Quebec

completeDrinking WaterCWWF
Federal contribution
$1.4M
$1,418,842
Federal share50%

of $2.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 27, 2017
201720182019
Built

Approved 5 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Mar 3, 2017(actual)
Construction end
Mar 31, 2019(actual)

Against the original forecast

  • Construction start6 months earlyforecast Sep 4, 2017

Also in Sainte-Geneviève-de-Batiscan

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48834 in the federal list. How to read these figures.