Renewal of water pipes

Saint-Adolphe-d'Howard, Quebec

completeDrinking WaterCWWF
Federal contribution
$815,765
Federal share44%

of $1.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 8, 2017
2017201820192020
Built

Approved 3 months before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Sep 4, 2018(actual)
Construction end
Dec 20, 2019(actual)

Against the original forecast

  • Construction start4 months lateforecast May 7, 2018

Also in Saint-Adolphe-d'Howard

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48837 in the federal list. How to read these figures.