Reconstruction of the main pumping station

Fossambault-sur-le-Lac, Quebec

completeWastewaterCWWF
Federal contribution
$1.9M
$1,889,292
Federal share50%

of $3.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 1, 2017
201720182019
Built

Approved 2 months before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Oct 13, 2017(actual)
Construction end
Jul 8, 2019(actual)

Against the original forecast

  • Construction start2 months lateforecast Aug 1, 2017

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48839 in the federal list. How to read these figures.