Renewal of water pipes

Price, Quebec

completeDrinking WaterCWWF
Federal contribution
$886,249
Federal share50%

of $1.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 3, 2017
Built

Approved 6 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Village of Price
Construction start
Aug 1, 2017(actual)
Construction end
Oct 6, 2017(actual)

Against the original forecast

  • Construction start16 months lateforecast Apr 1, 2016
  • Construction end18 months earlyforecast Mar 31, 2019

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48845 in the federal list. How to read these figures.