completeDrinking WaterCWWF
Federal contribution
$2.0M
$2,029,966
Federal share33%

of $6.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 1, 2017
20172018
Built

Approved 6 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Aug 7, 2017(actual)
Construction end
Oct 31, 2018(actual)

Against the original forecast

  • Construction start3 months lateforecast May 1, 2017
  • Construction end5 months earlyforecast Mar 31, 2019