Renewal of water pipes
Saint-Alexandre-de-Kamouraska, Quebec
Federal contribution
$292,229
Federal share50%
of $585.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 3, 2017
Built
Approved 6 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Municipality of Saint-Alexandre-de-Kamouraska
- Construction start
- Aug 10, 2017(actual)
- Construction end
- Nov 1, 2017(actual)
Against the original forecast
- Construction start16 months lateforecast Apr 1, 2016
- Construction end17 months earlyforecast Mar 31, 2019
Also in Saint-Alexandre-de-Kamouraska
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48862 in the federal list. How to read these figures.