Back to projects

Renewal of water pipes

Notre-Dame-du-Mont-Carmel, Quebec

completeDrinking WaterCWWF
Federal contribution
$674,228
Federal share50%

of $1.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 27, 2017
Built
Program
Clean Water and Wastewater Fund
Construction start
May 8, 2017(actual)
Construction end
Aug 10, 2017(actual)

Against the original forecast

  • Construction start4 weeks earlyforecast Jun 5, 2017
  • Construction end8 months earlyforecast Mar 31, 2018

Also in Notre-Dame-du-Mont-Carmel

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48863 in the federal list. How to read these figures.