Renewal of water pipes
Saint-Robert-Bellarmin, Quebec
Federal contribution
$578,233
Federal share50%
of $1.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 26, 2017
20172018
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Municipality of Saint-Robert-Bellarmin
- Construction start
- Aug 28, 2017(actual)
- Construction end
- Nov 30, 2018(actual)
Against the original forecast
- Construction start4 months lateforecast May 1, 2017
- Construction end3 weeks earlyforecast Dec 20, 2018
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48869 in the federal list. How to read these figures.