Schedule
Announced and approvedJan 27, 2017
2017
Built
Approved 6 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Parish Municipality of Saint-Barnabé
- Construction start
- May 4, 2017(actual)
- Construction end
- Nov 6, 2017(actual)
Against the original forecast
- Construction start5 weeks earlyforecast Jun 5, 2017
- Construction end5 months earlyforecast Mar 31, 2018