Renewal of water pipes

Princeville, Quebec

completeDrinking WaterCWWF
Federal contribution
$721,319
Federal share50%

of $1.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 20, 2017
20172018
Built

Approved 3 months before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Princeville
Construction start
Apr 2, 2018(actual)
Construction end
Nov 28, 2018(actual)

Against the original forecast

  • Construction start6 weeks earlyforecast May 14, 2018
  • Construction end5 weeks earlyforecast Dec 31, 2018

Also in Princeville

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48881 in the federal list. How to read these figures.