Renewal of water pipes

Saint-Camille-de-Lellis, Quebec

completeDrinking WaterCWWF
Federal contribution
$1.0M
$1,003,569
Federal share44%

of $2.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 17, 2017
Built

Approved 8 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Jul 4, 2017(actual)
Construction end
Oct 20, 2017(actual)

Against the original forecast

  • Construction start2 months lateforecast May 1, 2017
  • Construction end17 months earlyforecast Mar 31, 2019

Also in Saint-Camille-de-Lellis

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48882 in the federal list. How to read these figures.